Construction Progress

August 2023

The concrete structure works are almost 90% completed, we have already had the opportunity to enjoy the views from the 5th floor of buildings A and B. The brickwork on the interior and exterior started during this time and at the end of August 2023 the ground floor, floors 1 and 2 were completed. Also, the thermal insulation over the basement is almost complete and the installation work runs parallel in the basement and ground floor.

In this video, we also highlight the important infrastructure works taking place in the vicinity of the project. The passage from Doamna Ghica is to be opened at the beginning of September 2023, which will decongest the traffic in the area and ensure a travel time by car of approximately 10 minutes to the Aviatiei/ Pipera area. At the same time, work on the development of the promenade in front of the property has started, which will be connected to the existing promenade in the direction of Plumbuita Park – soon we will enjoy pedestrian access on the edge of the lake to the Plumbuita and Tei parks.
Play Video

Construction Progress - Video

Construction Progress - Photo

June 2023

The concrete structure works have been completed by around 45%. Building A slab over the first floor and Building B vertical elements for the first floor were being executed at the end of June 2023. Hydroinsulation and backfilling work around the basement walls in buildings A & B was completed as well as excavation works for the foundation of the retaining wall towards the north of the property have been started.

In this video we highlight that the balconies are connected with thermal break structural elements, which minimize heat loss transfer, help to reduce external noise in the apartments and ensure the prevention of mould forming over the long term.

Play Video

Construction Progress - Video

Construction Progress - Photo

April 2023

The excavation works have been completed and the two tower cranes installed. The foundation slab of the second basement has been completed and vertical elements, as well as the car ramp between basements 1 & 2, are currently under execution – the second basement accommodates technical spaces and a car access ramp to basement 2 of building C that is part of phase II development.

The foundation slab of the common first basement for buildings A & B was 80% completed (4 of 5 casting plots completed). In parallel, the reinforcement works of the vertical elements will follow – the first vertical elements have already been cast. The common basement for phase I development (buildings A & B) accommodates underground parking places, storage spaces, technical rooms, vertical circulation (lift and staircases) as well as waste management spaces with direct access from both the interior and exterior of the buildings.

Play Video

Construction Progress - Video

Construction Progress - Photo

February 2023

The drilling of reinforced concrete piles has been finished for excavation safety along our neighbour’s land borders. The reinforced concrete foundation piles under the buildings have been completed as well, together with all the quality tests including load capacity tests. Excavation works have been completed for Building A and will shortly be finalised for Building B as well. A layer of lean concrete was recently cast under the building’s foundation and the neighbour’s border retaining wall towards the southwest has been executed during this time. The main water connection as well as preparation for the later utility network connections has been executed within the site boundaries.

Play Video

Construction Progress - Video

Construction Progress - Photo

January 2023

The construction works at Quartier Azuga phase I started on the 14th of November 2022. Site organization, demolition of existing structures on the property as well as land clearing was completed by the end of 2022. The drilling of over 96 reinforced concrete piles started at the end of December 2022. These piles are used as safety excavation piles to secure the safety of the excavation pit and our neighbours’ constructions. Additional 61 reinforced concrete piles are being executed as deep foundation piles under the buildings – these deep foundation piles are essential for the stability of the buildings. Excavation works started at the beginning of January 2023, while the cleaning of the lake shore in front of the property was underway by the end of January 2023. 