Showroom

Play Video

Showroom - Video

Showroom - Photo

Quartier Azuga

Construction Progress

March 2024

Our project obtained the Building Permit for the 6th floor of buildings A and B at the beginning of March 2024. We initiated the structural works for the additional floor and completed them in the meantime. Additionally, the facade has been completed up to the 4th floor, and works on the metal balustrades and specially designed storage areas at the intermediate terraces are in progress.

Regarding interior finishes, tiling has been completed in the bathrooms on the ground floor of building A and is already in progress on the 1st floor. Underfloor heating systems and screed have been executed up to the 4th  floor in building A and up to the 3rd  floor in building B.

We are delighted to share this progress update with you and keep you informed about the evolution of your future home. Our team is dedicated to ensuring quality and efficiency in every detail of the project. We invite you to visit us and see the progress firsthand! Quartier Azuga – where every stage matters!

Play Video

Construction Progress - Video

Play Video

January 2024

The facade works in Building A have been completed up to the 4th floor and are progressing well in Building B. The PVC joinery has been fully mounted in both buildings A and B, meaning that inside works can move forward, regardless of the weather. 

In this video, we highlight two important aspects regarding the mounting of the PVC joinery. Firstly, the installation of the PVC joinery occurs at the outer limit of the brick walls, allowing for optimal thermal insulation and limitation of thermal bridges. Secondly, we’re using sealing tapes all around the joinery , offering extra thermal and sound insulation as well as better protection against the appearance of mold. 

Also, the underfloor heating system has been mounted up to the 3rd floor in building A, in tight coordination with plastering works, gypsum board partitioning and mechanical, electrical and plumbing-related works.

Play Video

Construction Progress - Video

November 2023

Façade works are well undergoing at building A, this will start shortly at building B as well. We’re using a thermosystem of 15 cm thickness to ensure superior thermal insulation and energy efficiency for the buildings.

The underfloor heating installation is ongoing at the intermediate floors in building A. We’re using Rehau systems, the best-performing underfloor heating system on the market. Typically, the underfloor heating pipes are placed above a layer of polystyrene boards; in our project, we’re using cellular concrete, which ensures better floor levelling, improved thermic transfer and superior sound insulation, as there are no air gaps between the floor slab and the underfloor heating system.

Furthermore, we highlight that the residents will benefit from modern elevators that can be called from the house via the smartphone, together with other functionalities, for an improved living experience.

Also, the showroom apartment is close to being finalised. We’re using high-quality finishes like ceramic tiles from Evoluzioni, flooring from Kronospan or sanitary objects from Grohe. Each room comes with an individual thermostat, allowing the residents to set different temperatures between the rooms for maximum comfort. Moreover, the decentralised ventilation heat recovery system allows for ventilation and air circulation in the apartment with minimal thermal transfer.
Play Video

Construction Progress - Video

Play Video

Construction Progress - Video

October 2023

The structural works have been completed in the meantime, also the brick works at the interior and exterior are circa 90% finalised. In parallel, the PVC joinery is executed at the intermediate levels of buildings A and B.

In this video, we emphasize that the project, among other things, uses joinery suitable for passive houses, with minimal heat loss that will be reflected in reduced maintenance costs and the extra comfort of the residents. The PVC joinery used is the Salamander bluEvolution 82 model with the optional Warm Edge spacer, traditionally, the spacing of the glass panes is made with aluminium, the Warm Edge spacer reduces the thermal transfer of the joinery by approximately 15% in comparison with the standard aluminium spacer.

The plastering works and the interior plasterboard partitions are carried out on the intermediate floors together with the installation works. Also, the roller shutters were installed on the garden apartments located on the ground floor. The external thermal insulation together with the works on the facade are scheduled to start at the beginning of November 2023.
Play Video

Construction Progress - Video

Construction Progress - Photo

August 2023

The concrete structure works are almost 90% completed, we have already had the opportunity to enjoy the views from the 5th floor of buildings A and B. The brickwork on the interior and exterior started during this time and at the end of August 2023 the ground floor, floors 1 and 2 were completed. Also, the thermal insulation over the basement is almost complete and the installation work runs parallel in the basement and ground floor.

In this video, we also highlight the important infrastructure works taking place in the vicinity of the project. The passage from Doamna Ghica is to be opened at the beginning of September 2023, which will decongest the traffic in the area and ensure a travel time by car of approximately 10 minutes to the Aviatiei/ Pipera area. At the same time, work on the development of the promenade in front of the property has started, which will be connected to the existing promenade in the direction of Plumbuita Park – soon we will enjoy pedestrian access on the edge of the lake to the Plumbuita and Tei parks.
Play Video

Construction Progress - Video

Construction Progress - Photo

June 2023

The concrete structure works have been completed by around 45%. Building A slab over the first floor and Building B vertical elements for the first floor were being executed at the end of June 2023. Hydroinsulation and backfilling work around the basement walls in buildings A & B was completed as well as excavation works for the foundation of the retaining wall towards the north of the property have been started.

In this video we highlight that the balconies are connected with thermal break structural elements, which minimize heat loss transfer, help to reduce external noise in the apartments and ensure the prevention of mould forming over the long term.

Play Video

Construction Progress - Video

Construction Progress - Photo

April 2023

The excavation works have been completed and the two tower cranes installed. The foundation slab of the second basement has been completed and vertical elements, as well as the car ramp between basements 1 & 2, are currently under execution – the second basement accommodates technical spaces and a car access ramp to basement 2 of building C that is part of phase II development.

The foundation slab of the common first basement for buildings A & B was 80% completed (4 of 5 casting plots completed). In parallel, the reinforcement works of the vertical elements will follow – the first vertical elements have already been cast. The common basement for phase I development (buildings A & B) accommodates underground parking places, storage spaces, technical rooms, vertical circulation (lift and staircases) as well as waste management spaces with direct access from both the interior and exterior of the buildings.

Play Video

Construction Progress - Video

Construction Progress - Photo

February 2023

The drilling of reinforced concrete piles has been finished for excavation safety along our neighbour’s land borders. The reinforced concrete foundation piles under the buildings have been completed as well, together with all the quality tests including load capacity tests. Excavation works have been completed for Building A and will shortly be finalised for Building B as well. A layer of lean concrete was recently cast under the building’s foundation and the neighbour’s border retaining wall towards the southwest has been executed during this time. The main water connection as well as preparation for the later utility network connections has been executed within the site boundaries.

Play Video

Construction Progress - Video

Construction Progress - Photo

January 2023

The construction works at Quartier Azuga phase I started on the 14th of November 2022. Site organization, demolition of existing structures on the property as well as land clearing was completed by the end of 2022. The drilling of over 96 reinforced concrete piles started at the end of December 2022. These piles are used as safety excavation piles to secure the safety of the excavation pit and our neighbours’ constructions. Additional 61 reinforced concrete piles are being executed as deep foundation piles under the buildings – these deep foundation piles are essential for the stability of the buildings. Excavation works started at the beginning of January 2023, while the cleaning of the lake shore in front of the property was underway by the end of January 2023. 

Play Video

Construction Progress - Video

Construction Progress - Photo

Are you interested in one of our apartments?

The showroom apartments are open for visits

Discover the apartments we have in the showroom.